Sizewell nuclear power plant is a nuclear power station in United Kingdom with 1 operating unit totalling 1,250 MW gross. The site has 5 units on record in total.

Operating4Retired6circle area ∝ site capacity Coastlines, borders and lakes: Natural Earth (1:10 million, public domain), which is generalised, so a coastal plant can sit a couple of kilometres off its true shoreline. Site positions: Global Nuclear Power Tracker.
Units on record
5
Operating
1
Operating capacity
1,250MW

Units

UnitStatusTypeModelGross MWOnline
Unit B Operating PWR SNUPPS 1,250 1995
Unit A1 Retired GCR MAGNOX 245 1966
Unit A2 Retired GCR MAGNOX 245 1966
Unit C1 Pre-construction PWR EPR 1,600 -
Unit C2 Pre-construction PWR EPR 1,600 -

Unit by unit

Each unit's rating, type and milestone dates as recorded by the Global Nuclear Power Tracker, with any correction we made to it. A dash or "not disclosed" means the source does not give the value.

Sizewell nuclear power plant B Operating

Reactor typePressurised water reactor (PWR)
ModelSNUPPS
Size classLarge
Gross capacity1,250MW
Net capacity1,198MW
Thermal output3,425MWt
Enrichment3–5% U-235
NSSS vendornot on record
OwnerEDF Energy Ltd100%
OperatorEDF Energy
Construction start18 Jul 1988
First criticality31 Jan 1995
Grid connection14 Feb 1995
Commercial operation22 Sep 1995

Live status, outage record and fuel chain for Sizewell nuclear power plant B

Sizewell nuclear power plant A1 Retired

Reactor typeGas-cooled reactor (GCR)
ModelMAGNOX
Size classSmall
Gross capacity245MW
Net capacity210MW
Thermal output1,010MWt
EnrichmentNatural uranium to 2.5–3.5% U-235no enrichment required
NSSS vendornot on record
OwnerNuclear Decommissioning Authority (United Kingdom)100%
OperatorMagnox
Construction start1 Apr 1961
First criticality1 Jun 1965
Grid connection21 Jan 1966
Commercial operation25 Mar 1966
Permanent shutdown31 Dec 2006

Sizewell nuclear power plant A2 Retired

Reactor typeGas-cooled reactor (GCR)
ModelMAGNOX
Size classSmall
Gross capacity245MW
Net capacity210MW
Thermal output1,010MWt
EnrichmentNatural uranium to 2.5–3.5% U-235no enrichment required
NSSS vendornot on record
OwnerNuclear Decommissioning Authority (United Kingdom)100%
OperatorMagnox
Construction start1 Apr 1961
First criticality1 Dec 1965
Grid connection9 Apr 1966
Commercial operation15 Sep 1966
Permanent shutdown31 Dec 2006

Sizewell nuclear power plant C1 Pre-construction

Corrected against a later source

GNPT types the unit as a pressurized heavy water reactor, but its model is the UK EPR, which is a pressurised water reactor. Sizewell C Ltd states that the UK EPR design used at Sizewell C is the same as at Hinkley Point C and that EPRs are a type of PWR. The fuel family follows the type: an EPR takes square-lattice PWR fuel, not CANDU-style bundles.

reactor_type: phwr → pwr · Sizewell C Ltd, Building Sizewell C (FAQ on the UK EPR design) · verified 2026-10-22

GNPT types the unit as a pressurized heavy water reactor, but its model is the UK EPR, which is a pressurised water reactor. Sizewell C Ltd states that the UK EPR design used at Sizewell C is the same as at Hinkley Point C and that EPRs are a type of PWR. The fuel family follows the type: an EPR takes square-lattice PWR fuel, not CANDU-style bundles.

fuel_family: phwr → pwr · Sizewell C Ltd, Building Sizewell C (FAQ on the UK EPR design) · verified 2026-10-22

Reactor typePressurised water reactor (PWR)
ModelEPR
Size classLarge
Gross capacity1,600MW
Net capacitynot disclosed
Thermal outputnot disclosed
Enrichment3–5% U-235
NSSS vendorFramatome
OwnerGovernment of United Kingdom83%
EDF Energy Ltd16%
Milestonesno dates on record

Sizewell nuclear power plant C2 Pre-construction

Corrected against a later source

GNPT types the unit as a pressurized heavy water reactor, but its model is the UK EPR, which is a pressurised water reactor. Sizewell C Ltd states that the UK EPR design used at Sizewell C is the same as at Hinkley Point C and that EPRs are a type of PWR. The fuel family follows the type: an EPR takes square-lattice PWR fuel, not CANDU-style bundles.

reactor_type: phwr → pwr · Sizewell C Ltd, Building Sizewell C (FAQ on the UK EPR design) · verified 2026-10-22

GNPT types the unit as a pressurized heavy water reactor, but its model is the UK EPR, which is a pressurised water reactor. Sizewell C Ltd states that the UK EPR design used at Sizewell C is the same as at Hinkley Point C and that EPRs are a type of PWR. The fuel family follows the type: an EPR takes square-lattice PWR fuel, not CANDU-style bundles.

fuel_family: phwr → pwr · Sizewell C Ltd, Building Sizewell C (FAQ on the UK EPR design) · verified 2026-10-22

Reactor typePressurised water reactor (PWR)
ModelEPR
Size classLarge
Gross capacity1,600MW
Net capacitynot disclosed
Thermal outputnot disclosed
Enrichment3–5% U-235
NSSS vendorFramatome
OwnerGovernment of United Kingdom83%
EDF Energy Ltd16%
Milestonesno dates on record

Sizewell nuclear power plant in context

By gross operating capacity Sizewell nuclear power plant is the 4th largest of 4 operating nuclear sites in the United Kingdom, holding 19% of the country's operating capacity, and ranks 129th of 172 worldwide.

Its operating unit started up in 1995; the unit is 31.0 years old, younger than the median of 37.0 in the United Kingdom.

The 3 units with both construction and grid dates on record took 4.8 to 6.6 years (median 5.0) from construction start to grid connection; the median across all reactors connected in the 1960s is 5.0 years.

The nearest other tracked nuclear sites are Gravelines nuclear power plant (138 km), Borssele nuclear power plant (168 km) and Doel nuclear power plant (207 km).

The current net rating of Unit B differs from its design net capacity by +0.8% (1,188 MW at design, 1,198 MW now).

Build time by unit

UnitConstruction startGrid connectionYearsFleet median, same decade
Unit A1196119664.85.0 (1960s)
Unit A2196119665.05.0 (1960s)
Unit B198819956.68.0 (1990s)

Nearest tracked nuclear sites

How these are worked out: ranks use gross operating capacity; ages count from the start-up year on record, as on the age page; build times run from construction start to grid connection, as on the build-times page; ratings are the tracker's net and design net capacity, as on the uprates page. Distances are straight-line between exact positions, so a site with only an approximate position gets none. A unit missing a date or a rating is left out of the figure that needs it.

Site detail
LocationEast Suffolk, England, United Kingdom
Coordinates52.2123, 1.6195
Elevationabout 20 mabove sea level
SettingOn the sea coast, 0.7 km from the water
RegionNorthern Europe
Units by status
Operating: 1
Retired: 2
Pre-construction: 2

Elevation is read at the listed coordinates from a 30 m terrain model (SRTM 30 m). Two independent models differ by a median of 6 m across our plants and by up to about 40 m on steep or coastal ground, and a point on a shoreline can read as sea level. Distance to the water is measured to a generalised 1:10 million coastline, so a few kilometres or less is not resolved. This is context, not a design-basis or flood-risk figure.

Owners & operators
Owners
Nuclear Decommissioning Authority (United Kingdom)
EDF Energy Ltd
Government of United Kingdom
Operators
Magnox
EDF Energy

Put this plant on your own page: embed a card, or compare it with another plant.

Sources

How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data

Try

Searches every page: 1,823 reactors, 592 plants, 158 fuel chain facilities, companies, designs, accidents and notes.