Torness nuclear power plant 1 is a gas-cooled reactor unit at Torness nuclear power plant in United Kingdom rated at 682 MW gross. It is operating. Commercial operation began 25 May 1988.
| Reactor type | Gas-cooled reactor (GCR) |
|---|---|
| Model | AGR |
| Size | Largeabove 300 MWe |
| Coolant | Carbon dioxide |
| Moderator | Graphite |
| Gross capacity | 682MW |
| Net capacity (reference) | 595MW |
| Net capacity (design) | 645MW |
| Thermal output | 1,623MWt |
| NSSS vendor | not on record |
| Typical enrichment | Natural uranium to 2.5–3.5% U-235 |
| Site | Torness nuclear power plant |
|---|---|
| Unit | 1 |
| Country | United Kingdom |
| Owner | EDF Energy Ltd100% |
| Operator | EDF Energy |
| Coordinates | 55.9679, -2.4086 |
- Westinghouse Electric Company AGR fuel elements
United Kingdom runs 8 operating units on AGR fuel. 1 fabricator is documented for it. No documented fabricator is based in United Kingdom. Only one supplier is documented. Country exposure
This unit runs on natural uranium, so its fuel chain has no enrichment step at all: mine → mill → conversion → fabrication. That is the shortest fuel chain of any commercial reactor type, and it makes the operator independent of the four organisations that control enrichment worldwide.
Timeline
- 1 Aug 1980Construction start
- 25 Mar 1988First criticality
- 25 May 1988Grid connection
- 25 May 1988Commercial operation
Other units at Torness nuclear power plant
| Unit | Status | Gross MW |
|---|---|---|
| Torness nuclear power plant 2 | 682 |
Other AGR units
15 units worldwide share this model designation.
| Unit | Country | Status | Gross MW |
|---|---|---|---|
| Hartlepool nuclear power plant A1 | United Kingdom | 655 | |
| Hartlepool nuclear power plant A2 | United Kingdom | 655 | |
| Heysham nuclear power plant A1 | United Kingdom | 625 | |
| Heysham nuclear power plant A2 | United Kingdom | 625 | |
| Heysham nuclear power plant B1 | United Kingdom | 680 | |
| Heysham nuclear power plant B2 | United Kingdom | 680 | |
| Torness nuclear power plant 2 | United Kingdom | 682 | |
| Dungeness nuclear power plant B1 | United Kingdom | Retired | 615 |
| Dungeness nuclear power plant B2 | United Kingdom | Retired | 615 |
| Hinkley Point nuclear power plant B1 | United Kingdom | Retired | 655 |
| Hinkley Point nuclear power plant B2 | United Kingdom | Retired | 655 |
| Hunterston nuclear power plant B1 | United Kingdom | Retired | 644 |
Sources
- Global Nuclear Power Tracker, Global Energy Monitor, August 2026 release , CC BY 4.0 · retrieved 2026-09-06 · this unit last researched by GEM on 2024-05-17
- GEM.wiki entry (further reading) , CC BY-SA 4.0, linked, not quoted
How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data