Leibstadt nuclear power plant
Leibstadt nuclear power plant is a boiling water reactor unit at Leibstadt nuclear power plant in Switzerland rated at 1,275 MW gross. It is operating. Commercial operation began 15 Dec 1984.
| Reactor type | Boiling water reactor (BWR) |
|---|---|
| Model | BWR-6 |
| Size | Largeabove 300 MWe |
| Coolant | Light water |
| Moderator | Light water |
| Gross capacity | 1,275MW |
| Net capacity (reference) | 1,233MW |
| Net capacity (design) | 960MW |
| Thermal output | 3,600MWt |
| NSSS vendor | GE Vernova Hitachi Nuclear Energyall vendors |
| Typical enrichment | 3–5% U-235 |
| Site | Leibstadt nuclear power plant |
|---|---|
| Unit | not stated |
| Country | Switzerland |
| Owner | Kernkraftwerk Leibstadt100% |
| Operator | Kernkraftwerk Leibstadt |
| Coordinates | 47.6012, 8.1845 |
- Framatome BWR fuel assemblies
- Global Nuclear Fuel BWR fuel assemblies
- Westinghouse Electric Company BWR fuel assemblies
Switzerland runs 1 operating unit on BWR fuel. 3 fabricators are documented for it. No documented fabricator is based in Switzerland. Country exposure
Enriched fuel means this unit sits downstream of five conversion plants and four enrichment operators holding 88% of world capacity between the top three.
Timeline
- 1 Jan 1974Construction start
- 9 Mar 1984First criticality
- 24 May 1984Grid connection
- 15 Dec 1984Commercial operation
Other BWR-6 units
5 units worldwide share this model designation.
| Unit | Country | Status | Gross MW |
|---|---|---|---|
| Kuosheng nuclear power plant 1 | Taiwan | Retired | 985 |
| Kuosheng nuclear power plant 2 | Taiwan | Retired | 985 |
| Montalto di Castro nuclear power plant 1 | Italy | Cancelled | 1,009 |
| Montalto di Castro nuclear power plant 2 | Italy | Cancelled | 1,009 |
Sources
- Global Nuclear Power Tracker, Global Energy Monitor, August 2026 release , CC BY 4.0 · retrieved 2026-09-06 · this unit last researched by GEM on 2024-05-09
- GEM.wiki entry (further reading) , CC BY-SA 4.0, linked, not quoted
How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data