Tokai nuclear power plant is a nuclear site in Japan with 2 units on record. None is currently operating.

Operating1Mothballed1Retired3circle area ∝ site capacitydashed = approximate position Coastlines, borders and lakes: Natural Earth (1:10 million, public domain), which is generalised, so a coastal plant can sit a couple of kilometres off its true shoreline. Site positions: Global Nuclear Power Tracker.
Units on record
2
Operating
0
Operating capacity
not disclosed
Country

Units

UnitStatusTypeModelGross MWOnline
Unit 1 Retired GCR MAGNOX 166 1966
Unit 2 Mothballed BWR BWR-5 1,100 1978

Unit by unit

Each unit's rating, type and milestone dates as recorded by the Global Nuclear Power Tracker, with any correction we made to it. A dash or "not disclosed" means the source does not give the value.

Tokai nuclear power plant 1 Retired

Reactor typeGas-cooled reactor (GCR)
ModelMAGNOX
Size classSmall
Gross capacity166MW
Net capacity137MW
Thermal output587MWt
EnrichmentNatural uranium to 2.5–3.5% U-235no enrichment required
NSSS vendornot on record
OwnerJapan Atomic Power Co100%
OperatorJapan Atomic Power
Construction start1 Mar 1961
First criticality4 May 1965
Grid connection10 Nov 1965
Commercial operation25 Jul 1966
Permanent shutdown31 Mar 1998

Tokai nuclear power plant 2 Mothballed

Corrected against a later source

GNPT records the unit as under construction, with a commercial operation date in the future. The Japan Atomic Industrial Forum's table of the status of Japan's nuclear power plants, as of 7 August 2026, lists Tokai-2 (BWR, 1,100 MWe) among the operable units, commercial operation 1978, in outage since 2011.03.11. Only Ohma, Higashidori-1 and Shimane-3 are in its under-construction table. The unit is complete and idle, like its sister units already recorded as mothballed, so it is not under construction. The commercial operation year is the JAIF's; the exact day is not given there, so only the year is recorded.

status: construction → mothballed · Japan Atomic Industrial Forum, Current Status of Nuclear Power Plants in Japan (as of 7 August 2026) · verified 2026-10-22

GNPT records the unit as under construction, with a commercial operation date in the future. The Japan Atomic Industrial Forum's table of the status of Japan's nuclear power plants, as of 7 August 2026, lists Tokai-2 (BWR, 1,100 MWe) among the operable units, commercial operation 1978, in outage since 2011.03.11. Only Ohma, Higashidori-1 and Shimane-3 are in its under-construction table. The unit is complete and idle, like its sister units already recorded as mothballed, so it is not under construction. The commercial operation year is the JAIF's; the exact day is not given there, so only the year is recorded.

commercial_operation: 2026-01-01 → 1978 · Japan Atomic Industrial Forum, Current Status of Nuclear Power Plants in Japan (as of 7 August 2026) · verified 2026-10-22

GNPT records the unit as under construction, with a commercial operation date in the future. The Japan Atomic Industrial Forum's table of the status of Japan's nuclear power plants, as of 7 August 2026, lists Tokai-2 (BWR, 1,100 MWe) among the operable units, commercial operation 1978, in outage since 2011.03.11. Only Ohma, Higashidori-1 and Shimane-3 are in its under-construction table. The unit is complete and idle, like its sister units already recorded as mothballed, so it is not under construction. The commercial operation year is the JAIF's; the exact day is not given there, so only the year is recorded.

start_year: 2026 → 1978 · Japan Atomic Industrial Forum, Current Status of Nuclear Power Plants in Japan (as of 7 August 2026) · verified 2026-10-22

Reactor typeBoiling water reactor (BWR)
ModelBWR-5
Size classLarge
Gross capacity1,100MW
Net capacity1,060MW
Thermal output3,293MWt
Enrichment3–5% U-235
NSSS vendorGE Vernova Hitachi Nuclear Energy
OwnerJapan Atomic Power Co100%
OperatorJapan Atomic Power
Construction start3 Oct 1973
First criticality18 Jan 1978
Grid connection13 Mar 1978
Commercial operation1978

Tokai nuclear power plant in context

The one unit with both construction and grid dates on record took 4.7 years from construction start to grid connection; the median across all reactors connected in the 1960s is 5.0 years.

The nearest other tracked nuclear sites are Kashiwazaki Kariwa nuclear power plant (211 km) and Onagawa nuclear power plant (234 km).

Build time by unit

UnitConstruction startGrid connectionYearsFleet median, same decade
Unit 1196119654.75.0 (1960s)

Nearest tracked nuclear sites

SiteCountryDistanceOperating GW gross
Kashiwazaki Kariwa nuclear power plantJapan211 km1.4
Onagawa nuclear power plantJapan234 km0.8

How these are worked out: ranks use gross operating capacity; ages count from the start-up year on record, as on the age page; build times run from construction start to grid connection, as on the build-times page; ratings are the tracker's net and design net capacity, as on the uprates page. Distances are straight-line between exact positions, so a site with only an approximate position gets none. A unit missing a date or a rating is left out of the figure that needs it.

Site detail
LocationHitachinaka, Ibaraki, Japan
Coordinates36.4215, 140.6028
Elevationabout 5 mabove sea level
SettingOn the sea coast, 0.7 km from the water
RegionEastern Asia
Units by status
Retired: 1
Mothballed: 1

Elevation is read at the listed coordinates from a 30 m terrain model (SRTM 30 m). Two independent models differ by a median of 6 m across our plants and by up to about 40 m on steep or coastal ground, and a point on a shoreline can read as sea level. Distance to the water is measured to a generalised 1:10 million coastline, so a few kilometres or less is not resolved. This is context, not a design-basis or flood-risk figure.

Owners & operators
Owners
Japan Atomic Power Co
Operators
Japan Atomic Power

Put this plant on your own page: embed a card, or compare it with another plant.