Skip to content

Seversk nuclear power plant

Seversk nuclear power plant is a nuclear site in Russia with 3 units on record. None is currently operating.

Under construction1Retired1circle area ∝ site capacity Coastlines, borders and lakes: Natural Earth (1:10 million, public domain), which is generalised, so a coastal plant can sit a couple of kilometres off its true shoreline. Site positions: Global Nuclear Power Tracker.
Units on record
3
Operating
0
Operating capacity
not disclosed
Country

Units

UnitStatusTypeModelGross MWOnline
Unit 1 Under construction FBR BREST-OD-300 320 2028
Unit 2 Cancelled PWR VVER V-510 1,255 -
Unit Original 1 Cancelled PWR VVER-TOI 1,200 -

Unit by unit

Each unit's rating, type and milestone dates as recorded by the Global Nuclear Power Tracker, with any correction we made to it. A dash or "not disclosed" means the source does not give the value.

Seversk nuclear power plant 1 Under construction

Reactor typeFast reactor (FBR)
ModelBREST-OD-300
Size classLarge
Gross capacity320MW
Net capacity300MW
Thermal output700MWt
Enrichment15–20% fissile, or plutonium
NSSS vendornot on record
OwnerRosatom100%
OperatorRosenergoatom
Construction start8 Jun 2021
Commercial operation1 Jan 2028

Seversk nuclear power plant 2 Cancelled

Reactor typePressurised water reactor (PWR)
ModelVVER V-510
Size classLarge
Gross capacity1,255MW
Net capacitynot disclosed
Thermal outputnot disclosed
Enrichment3–5% U-235
NSSS vendorRosatom
Cancelled2016
OwnerRosatom100%
OperatorRosenergoatom
Milestonesno dates on record

Seversk nuclear power plant Original 1 Cancelled

Reactor typePressurised water reactor (PWR)
ModelVVER-TOI
Size classLarge
Gross capacity1,200MW
Net capacitynot disclosed
Thermal outputnot disclosed
Enrichment3–5% U-235
NSSS vendorRosatom
Cancelled2016
OwnerRosatom100%
OperatorRosenergoatom
Milestonesno dates on record

Seversk nuclear power plant in context

No other nuclear site with an exact position in this dataset lies within 300 km.

How these are worked out: ranks use gross operating capacity; ages count from the start-up year on record, as on the age page; build times run from construction start to grid connection, as on the build-times page; ratings are the tracker's net and design net capacity, as on the uprates page. Distances are straight-line between exact positions, so a site with only an approximate position gets none. A unit missing a date or a rating is left out of the figure that needs it.

Site detail
LocationSeversk, Tomsk, Russia
Coordinates56.6583, 84.9482
Elevationabout 175 mabove sea level
SettingAbout 1,270 km from the sea
RegionEastern Europe
Units by status
Under construction: 1
Cancelled: 2

Elevation is read at the listed coordinates from a 30 m terrain model (SRTM 30 m). Two independent models differ by a median of 6 m across our plants and by up to about 40 m on steep or coastal ground, and a point on a shoreline can read as sea level. Distance to the water is measured to a generalised 1:10 million coastline, so a few kilometres or less is not resolved. This is context, not a design-basis or flood-risk figure.

Owners & operators
Owners
Rosatom
Operators
Rosenergoatom

Put this plant on your own page: embed a card, or compare it with another plant.

Sources

How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data

Try

Searches every page: 1,823 reactors, 592 plants, 158 fuel chain facilities, companies, designs, accidents and notes.