Takahama nuclear power plant 4 is a pressurised water reactor unit at Takahama nuclear power plant in Japan rated at 870 MW gross. It is operating. Commercial operation began 5 Jun 1985.

Specification
Reactor type Pressurised water reactor (PWR)
ModelM (3-loop)
Size classLarge
CoolantLight water
ModeratorLight water
Gross capacity870MW
Net capacity (reference)830MW
Net capacity (design)830MW
Thermal output2,660MWt
Typical enrichment3–5% U-235
Ownership & location
SiteTakahama nuclear power plant
Unit4
CountryJapan
OwnerKansai Electric Power Co100%
OperatorKansai Electric Power
Coordinates 35.5223, 135.5036
Fuel chain for this unit
Fuel form
Uranium dioxide pellets in zirconium-alloy cladding
Enrichment
3–5% U-235
Who makes this assembly
Upstream

Enriched fuel means this unit sits downstream of five conversion plants and four enrichment operators holding 88% of world capacity between the top three.

Fabricator capability is recorded against reactor type and model line, not against named units — utilities do not publish fuel contracts. See the fuel chain.

Timeline

  1. 19 Mar 1981Construction start
  2. 11 Oct 1984First criticality
  3. 1 Nov 1984Grid connection
  4. 5 Jun 1985Commercial operation

Other units at Takahama nuclear power plant

UnitStatusGross MW
Takahama nuclear power plant 1 Operating 826
Takahama nuclear power plant 2 Operating 826
Takahama nuclear power plant 3 Operating 870

Other M (3-loop) units

9 units worldwide share this model designation.

UnitCountryStatusGross MW
Ikata nuclear power plant 3 Japan Operating 890
Mihama nuclear power plant 3 Japan Operating 826
Sendai nuclear power plant 1 Japan Operating 890
Sendai nuclear power plant 2 Japan Operating 890
Takahama nuclear power plant 1 Japan Operating 826
Takahama nuclear power plant 2 Japan Operating 826
Takahama nuclear power plant 3 Japan Operating 870
Tomari nuclear power plant 3 Japan Under construction 912

Sources