Tver nuclear power plant
Tver nuclear power plant is a nuclear site in Russia with 4 units on record. None is currently operating.
Units
| Unit | Status | Type | Model | Gross MW | Online |
|---|---|---|---|---|---|
| Unit 1 | Cancelled | PWR | VVER-1200 | 1,200 | - |
| Unit 2 | Cancelled | PWR | VVER-1200 | 1,200 | - |
| Unit 3 | Cancelled | PWR | VVER-1200 | 1,200 | - |
| Unit 4 | Cancelled | PWR | VVER-1200 | 1,200 | - |
Unit by unit
Each unit's rating, type and milestone dates as recorded by the Global Nuclear Power Tracker, with any correction we made to it. A dash or "not disclosed" means the source does not give the value.
Tver nuclear power plant 1 Cancelled
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER-1200 |
| Size class | Large |
| Gross capacity | 1,200MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Cancelled | 2022 |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Milestones | no dates on record |
|---|
Tver nuclear power plant 2 Cancelled
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER-1200 |
| Size class | Large |
| Gross capacity | 1,200MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Cancelled | 2022 |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Milestones | no dates on record |
|---|
Tver nuclear power plant 3 Cancelled
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER-1200 |
| Size class | Large |
| Gross capacity | 1,200MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Cancelled | 2022 |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Milestones | no dates on record |
|---|
Tver nuclear power plant 4 Cancelled
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER-1200 |
| Size class | Large |
| Gross capacity | 1,200MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Cancelled | 2022 |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Milestones | no dates on record |
|---|
| Location | Udomlya, Tver, Russia |
|---|---|
| Coordinates | 57.8785, 35.0063approximate |
| Elevation | not given: the position is only approximate |
| Setting | not given: the position is only approximate |
| Region | Eastern Europe |
| Units by status | Cancelled: 4 |
| Owners | Rosatom |
|---|---|
| Operators | Rosenergoatom |
Put this plant on your own page: embed a card, or compare it with another plant.
Sources
- Global Nuclear Power Tracker, Global Energy Monitor, August 2026 release , CC BY 4.0 · retrieved 2026-09-06
- GEM.wiki entry (further reading) , CC BY-SA 4.0, linked, not quoted
How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data