Tatar nuclear power plant
Tatar nuclear power plant is a nuclear site in Russia with 4 units on record. None is currently operating.
Units
| Unit | Status | Type | Model | Gross MW | Online |
|---|---|---|---|---|---|
| Unit 1 | Cancelled (inferred) | PWR | VVER-TOI | 1,250 | - |
| Unit 2 | Cancelled (inferred) | PWR | VVER-TOI | 1,255 | - |
| Unit Original 1 | Cancelled | PWR | - | 950 | - |
| Unit Original 2 | Cancelled | PWR | - | 950 | - |
Unit by unit
Each unit's rating, type and milestone dates as recorded by the Global Nuclear Power Tracker, with any correction we made to it. A dash or "not disclosed" means the source does not give the value.
Tatar nuclear power plant 1 Cancelled (inferred)
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER-TOI |
| Size class | Large |
| Gross capacity | 1,250MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Cancelled | 2022 |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Milestones | no dates on record |
|---|
Tatar nuclear power plant 2 Cancelled (inferred)
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER-TOI |
| Size class | Large |
| Gross capacity | 1,255MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Cancelled | 2022 |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Milestones | no dates on record |
|---|
Tatar nuclear power plant Original 1 Cancelled
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | not disclosed |
| Size class | Large |
| Gross capacity | 950MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | 3–5% U-235 |
| NSSS vendor | not on record |
| Cancelled | 1990 |
| Operator | Rosenergoatom |
| Construction start | 1 Apr 1987 |
|---|
Tatar nuclear power plant Original 2 Cancelled
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | not disclosed |
| Size class | Large |
| Gross capacity | 950MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | 3–5% U-235 |
| NSSS vendor | not on record |
| Cancelled | 1990 |
| Operator | Rosenergoatom |
| Construction start | 1 May 1988 |
|---|
Tatar nuclear power plant in context
No other nuclear site with an exact position in this dataset lies within 300 km.
How these are worked out: ranks use gross operating capacity; ages count from the start-up year on record, as on the age page; build times run from construction start to grid connection, as on the build-times page; ratings are the tracker's net and design net capacity, as on the uprates page. Distances are straight-line between exact positions, so a site with only an approximate position gets none. A unit missing a date or a rating is left out of the figure that needs it.
| Location | Tatarstan, Russia |
|---|---|
| Coordinates | 55.4518, 51.2901 |
| Elevation | not available |
| Setting | not available |
| Region | Eastern Europe |
| Units by status | Cancelled: 4 |
| Owners | Rosatom |
|---|---|
| Operators | Rosenergoatom |
Put this plant on your own page: embed a card, or compare it with another plant.
Sources
- Global Nuclear Power Tracker, Global Energy Monitor, August 2026 release , CC BY 4.0 · retrieved 2026-09-06
- GEM.wiki entry (further reading) , CC BY-SA 4.0, linked, not quoted
How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data