Project Matador nuclear power plant 3
Pre-construction United States
Gross capacity
1,100MW
Project Matador nuclear power plant 3 is a pressurised water reactor unit at Project Matador nuclear power plant in United States rated at 1,100 MW gross. It is pre-construction. Commercial operation began 1 Jan 2035.
Specification
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | AP-1000 |
| Size class | Large |
| Coolant | Light water |
| Moderator | Light water |
| Gross capacity | 1,100MW |
| Net capacity (reference) | not disclosed |
| Net capacity (design) | not disclosed |
| Thermal output | not disclosed |
| Typical enrichment | 3–5% U-235 |
Ownership & location
| Site | Project Matador nuclear power plant |
|---|---|
| Unit | 3 |
| Country | United States |
| Owner | Fermi America LLC100% |
| Operator | Fermi America |
| Coordinates | 35.3046, -101.5987 |
Fuel chain for this unit
Fuel form
Uranium dioxide pellets in zirconium-alloy cladding
Enrichment
3–5% U-235
Who makes this assembly
- China National Nuclear Corporation PWR fuel assemblies
- ENUSA Industrias Avanzadas PWR and BWR fuel assemblies
- Framatome PWR fuel assemblies
- KEPCO Nuclear Fuel PWR fuel assemblies
- Mitsubishi Heavy Industries PWR fuel assemblies
- Westinghouse Electric Company PWR fuel assemblies
Upstream
Enriched fuel means this unit sits downstream of five conversion plants and four enrichment operators holding 88% of world capacity between the top three.
Fabricator capability is recorded against reactor type and model line, not against named units —
utilities do not publish fuel contracts. See the fuel chain.
Timeline
- 1 Jan 2035Commercial operation
Other units at Project Matador nuclear power plant
| Unit | Status | Gross MW |
|---|---|---|
| Project Matador nuclear power plant 1 | Pre-construction | 1,100 |
| Project Matador nuclear power plant 2 | Pre-construction | 1,100 |
| Project Matador nuclear power plant 4 | Pre-construction | 1,100 |
Other AP-1000 units
117 units worldwide share this model designation.
| Unit | Country | Status | Gross MW |
|---|---|---|---|
| Alvin W Vogtle nuclear power plant 3 | United States | 1,250 | |
| Alvin W Vogtle nuclear power plant 4 | United States | 1,250 | |
| Haiyang nuclear power plant 1-1 | China | 1,250 | |
| Haiyang nuclear power plant 1-2 | China | 1,250 | |
| Sanmen nuclear power plant 1-1 | China | 1,251 | |
| Sanmen nuclear power plant 1-2 | China | 1,251 | |
| Anhui Wuhu nuclear power plant 1-1 | China | Cancelled | 1,250 |
| Anhui Wuhu nuclear power plant 1-2 | China | Cancelled | 1,250 |
| Anhui Wuhu nuclear power plant 2-3 | China | Cancelled | 1,250 |
| Anhui Wuhu nuclear power plant 2-4 | China | Cancelled | 1,250 |
| Bellefonte nuclear power plant 3 | United States | Cancelled | 1,117 |
| Bellefonte nuclear power plant 4 | United States | Cancelled | 1,117 |
Sources
- Global Nuclear Power Tracker, Global Energy Monitor, August 2026 release — CC BY 4.0 · retrieved 2026-09-06 · this unit last researched by GEM on 2026-06-27
- GEM.wiki entry (further reading) — CC BY-SA 4.0 — linked, not quoted