Nuclear Power Demonstration (NPD) nuclear power plant

Retired Canada
Gross capacity
25MW

Nuclear Power Demonstration (NPD) nuclear power plant is a pressurised heavy water reactor unit at Nuclear Power Demonstration (NPD) nuclear power plant in Canada rated at 25 MW gross. It is retired. Commercial operation began 1 Oct 1962.

Specification
Reactor type Pressurised heavy water reactor (PHWR)
ModelCANDU
Size classLarge
CoolantHeavy water
ModeratorHeavy water
Gross capacity25MW
Net capacity (reference)22MW
Net capacity (design)17MW
Thermal output92MWt
Typical enrichmentNatural uranium, 0.71% U-235
Ownership & location
SiteNuclear Power Demonstration (NPD) nuclear power plant
Unitnot stated
CountryCanada
OwnerAECL100%
OperatorOntario Hydro
Coordinates 46.1867, -77.6578
Fuel chain for this unit
Fuel form
Natural uranium dioxide bundles
Enrichment
Natural uranium, 0.71% U-235 no enrichment required
Who makes this assembly
Upstream

This unit runs on natural uranium, so its fuel chain has no enrichment step at all: mine → mill → conversionfabrication. That is the shortest fuel chain of any commercial reactor type, and it makes the operator independent of the four organisations that control enrichment worldwide.

Fabricator capability is recorded against reactor type and model line, not against named units — utilities do not publish fuel contracts. See the fuel chain.

Timeline

  1. 1 Jan 1958Construction start
  2. 11 Apr 1962First criticality
  3. 4 Jun 1962Grid connection
  4. 1 Oct 1962Commercial operation
  5. 1 Aug 1987Permanent shutdown

Other CANDU units

3 units worldwide share this model designation.

UnitCountryStatusGross MW
Sellafield (Candu) nuclear power plant 1 United Kingdom Cancelled 740
Sellafield (Candu) nuclear power plant 2 United Kingdom Cancelled 740

Sources